Network Platforms - DB1-JB1 NLD Scheduled Maintenance 2026-04-05 Planned Maintenance NTP 1 – Maintenance details

Experiencing partially degraded performance

DB1-JB1 NLD Scheduled Maintenance 2026-04-05 Planned Maintenance NTP 1

Completed
Scheduled for April 05, 2026 at 3:00 AM – 2:00 PM

Affects

National Long Distance

Under maintenance from 3:00 AM to 2:00 PM

DB1 - JB1 - NLD 1 (N3 path) and NTP 1

Under maintenance from 3:00 AM to 2:00 PM

EL - BFN - NTP 1

Under maintenance from 3:00 AM to 2:00 PM

Updates
  • Completed
    April 05, 2026 at 2:00 PM
    Completed
    April 05, 2026 at 2:00 PM
    Maintenance has completed successfully
  • In progress
    April 05, 2026 at 3:00 AM
    In progress
    April 05, 2026 at 3:00 AM
    Maintenance is now in progress
  • Planned
    April 05, 2026 at 3:00 AM
    Planned
    April 05, 2026 at 3:00 AM

    Good day,

    Please be advised of the following scheduled maintenance.

    Maintenance Date and Time:

    Maintenance Start Time : 2026-04-05 05:00

    Maintenance End Time : 2026-04-05 16:00

    Maintenance Description:

    The supplier will be conducting service-affecting maintenance to carry out permanent repairs due to limited spare fibres on this segment. The work will take place between BFN IS DC and Reddersburg.

    Impact Description

    No impact is expected to client services, as traffic will fail over to the redundant paths.

    Should you have any queries, please log a ticket with our support desk by emailing support@networkplatforms.co.za

    Regards
    Network Platforms