Network Platforms - JB1 Data Centre 2 Cable Management and Clean up 18 September 2024 – Maintenance details
Experiencing partially degraded performance
JB1 Data Centre 2 Cable Management and Clean up 18 September 2024
Completed
Scheduled for September 18, 2024 at 8:00 PM – 9:59 PM
Affects
General
Under maintenance from 8:00 PM to 9:59 PM
General Notifications
Under maintenance from 8:00 PM to 9:59 PM
Updates
Completed
September 18, 2024 at 9:59 PM
Completed
September 18, 2024 at 9:59 PM
Maintenance has completed successfully
In progress
September 18, 2024 at 8:00 PM
In progress
September 18, 2024 at 8:00 PM
Maintenance is now in progress
Planned
September 18, 2024 at 8:00 PM
Planned
September 18, 2024 at 8:00 PM
Dear Network Platforms Clients
Affected Service: Connectivity through Johannesburg Data Centre Description: JB1 Data Centre 2 Cable Management and Clean-up
Impact: Intermittent connectivity as cabling is moved or re-routed.
Scope of Work: Network Platforms is embarking on an exercise to clean up and fix the cabling in JB1 DC 2 at the Johannesburg Data Centre. Clients will experience intermittent connectivity during the maintenance windows as cables are moved or re-routed through the cable management units.
Clients not co-located in DC2 and with protected services will remain unaffected.
Activity Window:
Dates: 18 September 2024
Planned Event Start time: 22:00 Planned Event End time: 23:59
Should you have any concerns or questions in this regard, please do not hesitate to contact us at support@networkplatforms.co.za.