Network Platforms - Liquid Emergency Maintenance NLD JB1-DB1 - 21st October 18H00 – Maintenance details

Liquid Emergency Maintenance NLD JB1-DB1 - 21st October 18H00

Completed
Scheduled for October 21, 2024 at 4:00 PM – October 22, 2024 at 4:00 AM

Affects

National Long Distance

Under maintenance from 4:00 PM to 4:00 AM

DB1- JB1 - Liquid

Under maintenance from 4:00 PM to 4:00 AM

Updates
  • Completed
    October 22, 2024 at 4:00 AM
    Completed
    October 22, 2024 at 4:00 AM
    Maintenance has completed successfully
  • In progress
    October 21, 2024 at 4:00 PM
    In progress
    October 21, 2024 at 4:00 PM
    Maintenance is now in progress
  • Planned
    October 21, 2024 at 4:00 PM
    Planned
    October 21, 2024 at 4:00 PM

    Dear Customer,

     

    Please take note of a Liquid Emergency Change scheduled on Marianhill between New Germany and PMB on NLD1 section 6 on the 21st October  2024 from 18h00 to 22nd October 2014 at 06h00. They urgently need to repair damaged cables at Marianhill that were damaged by excavator during the floods. Cables were relocated and new cables were floated . They are currently at risk of getting damaged by vandalism or fire as the cable is lying above ground.

      

    IMPACT: Services will be down for a maximum duration of 2Hrs during the change.

     

    Affected Services: NLD JB1-DB1

     

    Reason for Change:

     

    To repair damaged cables at Marianhill that were damaged by excavator during the floods. Cables were relocated and new cables were floated .We are currently at risk of getting damaged by vandalism or fire as cable is lying above ground.

    Clients with protected services will be unaffected by this maintenance.

    If you have any questions regarding this maintenance, please email support@networkplatforms.co.za

    Regards,

    Network Platforms