Network Platforms - Seacom Emergency Maintenance NLD DB1-JB1 - 5th March 18H00 – Maintenance details

Seacom Emergency Maintenance NLD DB1-JB1 - 5th March 18H00

Completed
Scheduled for March 05, 2025 at 4:00 PM – March 06, 2025 at 12:00 AM

Affects

National Long Distance

Under maintenance from 4:00 PM to 12:00 AM

DB1 - JB1 - Seacom

Under maintenance from 4:00 PM to 12:00 AM

Updates
  • Completed
    March 06, 2025 at 12:00 AM
    Completed
    March 06, 2025 at 12:00 AM
    Maintenance has completed successfully
  • In progress
    March 05, 2025 at 4:00 PM
    In progress
    March 05, 2025 at 4:00 PM
    Maintenance is now in progress
  • Planned
    March 05, 2025 at 4:00 PM
    Planned
    March 05, 2025 at 4:00 PM

    Dear Customer,

    This serves to inform you that the SEACOM provider has scheduled an emergency service affecting planned activity. During the event mentioned, NLD DB1 - JB1 - Seacom will be affected as follows:

    Activity window:

    Start Date & Time: 18:00 5th March 2025

    End Date & Time: 02:00 6th March 2025

    Expected Downtime: 5 Hours

    SCOPE: To do permanent repair on damaged optic fibre infrastructure between Ladysmith and Estcourt


    Services Affected:

    DB1 - JB1 - Seacom