Network Platforms - Durban Core Router Maintenance 5-6 September 25 – Maintenance details

Durban Core Router Maintenance 5-6 September 25

Completed
Scheduled for September 05, 2025 at 8:00 PM – September 06, 2025 at 4:00 AM

Affects

Core Network

Under maintenance from 8:00 PM to 4:00 AM

DB1 Edge Routers

Under maintenance from 8:00 PM to 4:00 AM

DB1 Switches

Under maintenance from 8:00 PM to 4:00 AM

IP Transit

Under maintenance from 8:00 PM to 4:00 AM

General Status IP Transit

Under maintenance from 8:00 PM to 4:00 AM

Peering

Under maintenance from 8:00 PM to 4:00 AM

Updates
  • Completed
    September 06, 2025 at 4:00 AM
    Completed
    September 06, 2025 at 4:00 AM
    Maintenance has completed successfully
  • In progress
    September 05, 2025 at 8:00 PM
    In progress
    September 05, 2025 at 8:00 PM
    Maintenance is now in progress
  • Planned
    September 05, 2025 at 8:00 PM
    Planned
    September 05, 2025 at 8:00 PM

    Scheduled Maintenance Notification

    Dates: Friday, 5 September to Saturday, 6 September 2025
    Time: 22:01 – 06:00

    We will be replacing the Cisco Edge routers in Durban with Juniper routers during the scheduled maintenance window.


    Plan of Action

    1. Migrate all services from DB1-EDGE-2 (Cisco) to the existing DB1-EDGE-1 (Juniper).

    2. Replace DB1-EDGE-2 (Cisco) with the new DB1-EDGE-2 (Juniper).

    3. Migrate all services from DB1-EDGE-3 (Cisco) to the new DB1-EDGE-2 (Juniper).

    4. Decommission and remove DB1-EDGE-3 (Cisco).


    Impact

    • Clients may experience brief service interruptions while services are migrated from the Cisco routers to the Juniper routers.

    • All efforts will be made to minimize downtime.

    Affected Services (Durban):

    • IP Transit

    • National Long Distance

    • International Long Distance

    • General connectivity in the Durban Data Centre


    Fallback Plan

    If issues arise during the migration, the fallback will be to remove the Juniper equipment and reinstall the Cisco routers.