Scheduled for February 06, 2026 at 8:00 PM – February 07, 2026 at 3:00 AM
Affects
Virtual Hosting
Under maintenance from 8:00 PM to 3:00 AM
JB1 - iSCSI SAN
Under maintenance from 8:00 PM to 3:00 AM
JB1 - VM Nodes
Under maintenance from 8:00 PM to 3:00 AM
JB1 - vSAN
Under maintenance from 8:00 PM to 3:00 AM
vCloud Director Portal
Under maintenance from 8:00 PM to 3:00 AM
Voice and PBX
Under maintenance from 8:00 PM to 3:00 AM
Updates
Completed
February 07, 2026 at 3:00 AM
Completed
February 07, 2026 at 3:00 AM
Maintenance has completed successfully
In progress
February 06, 2026 at 8:00 PM
In progress
February 06, 2026 at 8:00 PM
Maintenance is now in progress
Planned
February 06, 2026 at 8:00 PM
Planned
February 06, 2026 at 8:00 PM
Planned Maintenance Notice
Johannesburg Virtual Hosting Environment
Maintenance Window
Dates: 6 – 9 February 2025
Schedule:
Friday, 6 February 2025: 22:00 – 05:00 (7 February)
Saturday, 7 February 2025: 22:00 – 05:00 (8 February)
Sunday, 8 February 2025: 15:00 – 05:00 (9 February)
Description
Network Platforms will be performing planned maintenance to relocate the Virtual Nodes and Storage Infrastructure from Teraco JB1 Datacentre to the Digital Parks Africa Samrand Datacentre.
Expected Impact
No service downtime is anticipated for client virtual machines or hosted services.
Virtual machines will be live-migrated to active nodes while individual nodes are being relocated.
Backup schedules may be temporarily disrupted during the maintenance windows.
In the event of unforeseen issues, all affected systems will be reverted to their current operational location to ensure service continuity.
Additional Information
Network Platforms engineers will closely monitor all systems throughout the maintenance period to ensure stability and performance. Should any unexpected impact occur, clients will be notified accordingly.
If you have any questions or concerns, please contact our support team.