Network Platforms - DB1-CT1 NLD Scheduled Maintenance 2026-04-09 Planned Maintenance NLD4 โ€“ Maintenance details

DB1-CT1 NLD Scheduled Maintenance 2026-04-09 Planned Maintenance NLD4

Completed
Scheduled for April 09, 2026 at 4:00 AM โ€“ย 4:00 PM

Affects

National Long Distance

Under maintenance from 4:00 AM to 4:00 PM

CT1 - JB1 - NLD 2/3/4 (N1 path)

Under maintenance from 4:00 AM to 4:00 PM

Updates
  • Completed
    April 09, 2026 at 4:00 PM
    Completed
    April 09, 2026 at 4:00 PM
    Maintenance has completed successfully
  • In progress
    April 09, 2026 at 4:00 AM
    In progress
    April 09, 2026 at 4:00 AM
    Maintenance is now in progress
  • Planned
    April 09, 2026 at 4:00 AM
    Planned
    April 09, 2026 at 4:00 AM

    Good day,

    Please be advised of the following scheduled maintenance:

    Maintenance Date and Time:

    Maintenance Start Time : 2026-04-09 06:00

    Maintenance End Time : 2026-04-09 18:00

    Maintenance Description:

    The supplier urgently needs to relocate the infrastructure. Contractors are busy uprooting trees along LIT infrastructure on the NLD4, and they are damaging the infrastructure. A security wall is being erected along the perimeter of erf 8645 Smith street in Worcester and the infrastructure is too close to the wall and needs to be relocated urgently.

    Impact Description:

    No impact is expected on client services, as traffic will fail over to the redundant paths.

    Should you have any queries, please log a ticket with our support desk by emailing support@networkplatforms.co.za

    Regards

    Network Platforms