All our paths are fully operational today with full redundancy. The failure on one of the paths was due to a cable break between Klip and Parklands. The path was operational after the provider engineers completed splicing.
Incident Start Time:* 2025-07-30 11:05:00 Incident End Time:* 2025-07-31 00:30:00
Regards
Network Platforms
Investigating
Investigating
Due to a Fibre path failures between JB1 and CT1 Data Centres between 11:05 and 11:10am , Customers were at risk due to the path failure
The service has since restored we are monitoring the link.