Network Platforms - Liquid Maintenance NLD JB1-DB1 23rd July 2024 18H00 – Maintenance details

Liquid Maintenance NLD JB1-DB1 23rd July 2024 18H00

Completed
Scheduled for July 23, 2024 at 4:00 PM – 10:00 PM

Affects

National Long Distance

Under maintenance from 4:00 PM to 10:00 PM

DB1- JB1 - Liquid

Under maintenance from 4:00 PM to 10:00 PM

Updates
  • Completed
    July 23, 2024 at 10:00 PM
    Completed
    July 23, 2024 at 10:00 PM
    Maintenance has completed successfully
  • In progress
    July 23, 2024 at 4:00 PM
    In progress
    July 23, 2024 at 4:00 PM
    Maintenance is now in progress
  • Planned
    July 23, 2024 at 4:00 PM
    Planned
    July 23, 2024 at 4:00 PM

    Scheduled:

    Start : 23rd July 18H00

    End : 23th July 23H59

    Please take note of a Liquid Planned Change scheduled to relocate the NLD1 fibre route between Harrismith and Ladysmith (Van Reenen Pass). The road contractor will start core drilling on top of our route so due to road construction they have to do this change as the infrastructure will be damaged by the contractors if they do not relocate on the 23rd July 2024 from 18:00 - 23rd July 2024 at 23:59.

    Impact: Services will be down for a maximum duration of 3Hrs, other services will experience an intermittent 50ms switching hit.