Network Platforms - cPanel servers - Migration – Maintenance details

cPanel servers - Migration

Completed
Scheduled for August 24, 2024 at 8:00 PM – August 25, 2024 at 4:00 AM

Affects

Web Hosting

Under maintenance from 8:00 PM to 4:00 AM

cPanel Web Server

Under maintenance from 8:00 PM to 4:00 AM

Updates
  • Completed
    August 25, 2024 at 4:00 AM
    Completed
    August 25, 2024 at 4:00 AM
    Maintenance has completed successfully
  • In progress
    August 24, 2024 at 8:00 PM
    In progress
    August 24, 2024 at 8:00 PM
    Maintenance is now in progress
  • Planned
    August 24, 2024 at 8:00 PM
    Planned
    August 24, 2024 at 8:00 PM

    Scheduled Date : 24th August 22H00

    Estimated Time : 8 Hours

    We will be migrating cPanel servers to a new virtualization cluster. Estimated downtime per server is 90 minutes.

    Plan of Action:

    1. Shutdown VM on old cluster

    2. Replicate data to new cluster

    3. Power on VM on the new cluster / Fixing interfaces and grub bootloader

    4. Test

    Rollback plan:

    1. Power off VM on the new cluster

    2. Power on VM on the old cluster