Network Platforms - Liquid eFTTB Planned Maintenance scheduled for WESTVILLE POP 6 February 2025 – Maintenance details

Liquid eFTTB Planned Maintenance scheduled for WESTVILLE POP 6 February 2025

Completed
Scheduled for February 06, 2025 at 8:00 PM – February 07, 2025 at 12:00 AM

Affects

Business FTTB

Under maintenance from 8:00 PM to 12:00 AM

Liquid eFTTB - DB1

Under maintenance from 8:00 PM to 12:00 AM

Updates
  • Completed
    February 07, 2025 at 12:00 AM
    Completed
    February 07, 2025 at 12:00 AM
    Maintenance has completed successfully
  • In progress
    February 06, 2025 at 8:00 PM
    In progress
    February 06, 2025 at 8:00 PM
    Maintenance is now in progress
  • Planned
    February 06, 2025 at 8:00 PM
    Planned
    February 06, 2025 at 8:00 PM

    Dear Customer,

    Please take note of a Liquid eFTTB DBN Planned Change scheduled at WESTVILLE POP on the 6th February 2025 from 22:00 to 7th February 2025 at 02:00 .We need to upgrade the ASR920 device from IOS version from 17.03.05 to 17.06.04. The device is misbehaving due to a cisco bug on the current version.

    IMPACT: Services will be down for a maximum duration of 30Minutes.


    Affected Services

    Liquid eFTTB DBN Circuit connected to WESTVILLE POP

     

    Reason For Change

    To upgrade the ASR920 device from IOS version from 17.03.05 to 17.06.04. The device is misbehaving due to a cisco bug on the current version.

    Implementation Plan

    IOS Upgrade from 17.03.05 to 17.06.04

    1. NOC to copy IOS image files for version 17.06.04 to device

    2. Activate 17.06.04 device and reload

    3. Verify the services after IOS upgraded

    ROLL BACK PLAN

    Roll back to previous version 17.03.05.