Teraco PDU replacement DC4 cabinet P01 Sunday 16 March
Completed
Scheduled for March 16, 2025 at 8:00 AM – 10:58 AM
Affects
Core Network
Under maintenance from 8:00 AM to 10:58 AM
JB1 Switches
Under maintenance from 8:00 AM to 10:58 AM
General
Under maintenance from 8:00 AM to 10:58 AM
General Notifications
Under maintenance from 8:00 AM to 10:58 AM
Updates
Completed
March 16, 2025 at 10:58 AM
Completed
March 16, 2025 at 10:58 AM
Maintenance has completed successfully
In progress
March 16, 2025 at 10:04 AM
In progress
March 16, 2025 at 10:04 AM
Maintenance is now in progress.
Completed
March 16, 2025 at 10:00 AM
Completed
March 16, 2025 at 10:00 AM
Maintenance has completed successfully
In progress
March 16, 2025 at 8:00 AM
In progress
March 16, 2025 at 8:00 AM
Maintenance is now in progress
Planned
March 16, 2025 at 8:00 AM
Planned
March 16, 2025 at 8:00 AM
Scheduled Date: 16 March 2025
Scheduled Time: 10H00
Expected Duration: 60 minutes with a short outage on the PDU being changed
Teraco have detected an issue with the current power PDU's in cabinet DC4-P01, which is resulting in them being unable to perform essential tasks on them, such as firmware updates, nor generating PDU events logs. This hinders their ability to manage and monitor our systems effectively and also pose a security risk due to the inability to update the firmware.
They would like to replace the PDU's with Raritan PDU units in the maintenance slot, they will be doing one PDU at a time, ensuring that dual-connected devices remain online.
As there is a high risk of complete power loss, we will have an engineer at the data centre overseeing the change.