Network Platforms - Major Electrical Maintenance at JB1 Isando Data Centre for DC6 TEM4 A and B Feed – Maintenance details
All systems operational
Major Electrical Maintenance at JB1 Isando Data Centre for DC6 TEM4 A and B Feed
Completed
Scheduled for April 12, 2025 at 6:00 AM – 4:00 PM
Affects
General
Under maintenance from 6:00 AM to 4:00 PM
General Notifications
Under maintenance from 6:00 AM to 4:00 PM
Updates
Completed
April 12, 2025 at 4:00 PM
Completed
April 12, 2025 at 4:00 PM
Maintenance has completed successfully
In progress
April 12, 2025 at 6:00 AM
In progress
April 12, 2025 at 6:00 AM
Maintenance is now in progress
Planned
April 12, 2025 at 6:00 AM
Planned
April 12, 2025 at 6:00 AM
MAINTENANCE NOTIFICATION: Major Electrical Maintenance at JB1 Isando Data Centre for TEM4 A and B Feed
Dear Client
Teraco have scheduled a Planned Major Electrical Maintenance at the JB1 Isando Data Centre, the details are as follows:
Description
JB1 TEM4 A and B Feed Electrical Infrastructure Maintenance
DC6 and Carrier Hotel 4
Date
12 April 2025, 08:00 to 18:00
SERVICE IMPACT
No planned power interruptions to any dual corded devices with STS's installed upstream from the PDPs.
No planned power interruptions to single corded devices with STS's installed upstream from the PDPs. (We however still recommend that Clients install ATS’s for single corded devices)
STS's are installed upstream from the PDP’s but only one power source will be active at a time.
Only one feed will be worked on at a time ensuring N resilience at all times.
No client installations to be undertaken during this period.
Maintenance roll back plan in place to mitigate any unplanned or unforeseen circumstances.