Scheduled for May 17, 2025 at 6:00 AM – 4:00 PM about 10 hours
Planned
May 17, 2025 at 6:00 AM
Planned
May 17, 2025 at 6:00 AM
Scheduled Date: 17 May 2025
Scheduled Time: 08H00 to 18H00
Expected Duration: 10 Hours
Teraco has planned scheduled Major Electrical Maintenance at the JB1 East Isando Data Centre TEM3 A FEED.
The details are as follows:
Description
Data Centre 4
Data Centre 5
SERVICE IMPACT
During planned Major Electrical Work at JB1 East the TEM3 MLV A Feed supply will be switched off and isolated.
TEM3 MLV B Feed will remain available. No redundancy as only TEM3 MLV B Feed will be the source of power.
Dual-corded devices will not be affected as B feed will be available. Customer to ensure dual corded device is split over A and B PDU’s.
All single-corded devices connected to the A feed will be off. Customers advised to install ATS units or move power connections to the B feed in advance.
Only one feed will be worked on at a time ensuring N resilience at all times.
No client installations to be undertaken during this period.
Maintenance roll back plan in place to mitigate any unplanned or unforeseen circumstances.